Work Orders & Facilities Modification Request ("FMR")

Maintenance Work Order Procedure

 

Where can I submit a Work Order?

Work orders may be submitted through Facilitron by clicking HERE

Submit a Work Order

What is a Work Order?

Routine repair and maintenance, replace, vandalism, and/or Williams inspection.**
 
  • Step 1: Custodian or site designee submits work order (Facilitron).
  • Step 2: Maintenance will receive and order and assist it as necessary.
  • Step 3: The shop schedules the work as necessary.
  • Step 4: After work is completed, the work order will be closed.
 
Additional questions: Doug Jones, Operations Supervisor, (909) 418-6591
 
**Not all work orders are an emergency
**Current work order backlog is 930

Facilities Modification Request ("FMR") Procedure

 

Where can I submit a Facilities Modification Request ("FMR")?

To submit a Facilities Modification Request ("FMR"), Click HERE to download the FMR forms.  Upload completed FMR forms and supporting documents with the work order.   

FMR Forms

What is an FMR? 

Site/Capital Improvements or upgrade.

  • Step 1: Fill out the FMR form and submit a work order.
  • Step 2: Feasibility Study to be completed by the Facilities Planning and Operations department.
  • Step 3: FMR Determination/Status Form to the site for status and determination.
  • Step 4: Project established.
  • Step 5: Planning phase.
  • Step 6: Bidding phase.
  • Step 7: Construction phase.
  • Step 8: Post-construction sign off (Notice of Completion)